Description of the Works
The Building Management Systems Controls are being upgraded in the above buildings.
Stage 1 - Install network points in the buildings adjacent to the controls that are due to be upgraded.
Quest has a single network point being installed.
The Admin Building has a single network point being installed on the 1st floor corridor.
Textiles has a single network point being installed on the top floor.
3D will not require any network points.
Fine Art requires 17 network points to be installed.
Once the network has been installed, the next stage of the project will being. An update will be circulated before this stage begins.
Timescale
The works will start of 23 April to 9 May 2025 - network installation will be taking place.
How can I get more information and help?
The Estates and Facilities Management team member looking after the task is detailed below and can be contacted about any difficulties experienced because of these works.
Rob Farmer - Controls and Systems Support Engineer
Mobile - 07850 938619
Email - r.farmer@lboro.ac.uk